Question : How to configure two types of update timings for VSE 8.7i via EPO server?

Is it possible to set two different types of AutoUpdate timings in VSE 8.7i using EPO server?
Eg. I want the servers to update at 0700hrs while the workstations to update at 1000hrs.

Thank you.

Answer : How to configure two types of update timings for VSE 8.7i via EPO server?

In the ePO, go to the container you want to set the tasks for and then create a new update task, set the schedule and then you're done. I think with 8.7 it shows in the UI.