Hi,

I started the process of migration from SBS 2003 to SBS 2008.

I have already run the Migration Preparation Tool.

The time limit to migrate is 21 days.

But, now the issue has been fixed on the SBS 2003 server and we will not be migrating.

I took the SBS 2008 server off the network.

Will it still shut down after 21 days?

Regards.

Answer : SBS Migration 21 days patch

You didn't say you had got that far.  How can your SBS 2003 be the only SBS in the domain when you've used the answer file to introduce a 2008 SBS already?  You need to turn your SBS 2008 on, then transfer the FSMO roles to the 2003 SBS, then demote the 2008 server to member server, then disjoin it from the domain.