Question : Export Project Tasks assigned to a single individual
I want to export the tasks assigned to a single individual to a separate Excel file. Out of my very large project, I want to filter on the tasks assigned to an individual and then Export ONLY those tasks shown by the filter to an Excel file.
I already have my export map saved, but none of the filters in the Save map allow me to filter by tasks assigned to a single resource name.
How do I do this? (preferably how do I do it in code...but I can record a macro if shown how to do it in the GUI)
Answer : Export Project Tasks assigned to a single individual
You either need a Handles BTNCheckPrevious.Command at the end of the sub, or an OnCommand="BTNCheckPreviou
s_Command"
in the HTML. Since this is not a top-level command, I would go with the OnCommand in the HTML.
Random Solutions
Problem Installing Windows Server 2003 Enterprise Edition on Dell Precision 390
TRANSACT SQL: COALESCE FUNCTION - DATE RANGES AND NULL VALUES
bootable usb
Move jpg files from file server and create shortcut
How do I embed ajax calendar extender in asp.net gridview correctly?
How to copy a 150 Gb database across the country?
Big DNS problem, some internet servers reporting non-existent domain
Windows 7, Domain: Admin cannot save to C drive from Outlook.
VB.NET simple SendMail program error: System.Net.Mail.SmtpExcept
ion: Failure sending mail
jQuery - AJAX Call when a Checkbox is Checked